You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the…
The correct answer is C. Select the Mark Task as Milestone check box. See the full explanation below for the reasoning.
Question
You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?
Options
- ARemove the predecessor assignments.
- BClick the Insert Milestone button.
- CSelect the Mark Task as Milestone check box.
- DChange Work to zero hours.
How the community answered
(19 responses)- A11% (2)
- B16% (3)
- C68% (13)
- D5% (1)