You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the…

The correct answer is C. Select the Mark Task as Milestone check box. See the full explanation below for the reasoning.

Question

You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?

Options

  • ARemove the predecessor assignments.
  • BClick the Insert Milestone button.
  • CSelect the Mark Task as Milestone check box.
  • DChange Work to zero hours.

How the community answered

(19 responses)
  • A
    11% (2)
  • B
    16% (3)
  • C
    68% (13)
  • D
    5% (1)