Question

You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?

Options

  • ARemove the predecessor assignments.
  • BClick the Insert Milestone button.
  • CSelect the Mark Task as Milestone check box.
  • DChange Work to zero hours.