Microsoft
70-178 · Question #39
70-178 Question #39: Real Exam Question with Answer & Explanation
Sign in or unlock 70-178 to reveal the answer and full explanation for question #39. The question stem and answer options stay visible for context.
Question
You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?
Options
- ARemove the predecessor assignments.
- BClick the Insert Milestone button.
- CSelect the Mark Task as Milestone check box.
- DChange Work to zero hours.
Unlock 70-178 to see the answer
You've previewed enough free 70-178 questions. Unlock 70-178 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.