Microsoft
70-178 · Question #38
70-178 Question #38: Real Exam Question with Answer & Explanation
The correct answer is C. In the Start Date field, type 9/13/2010.. See the full explanation below for the reasoning.
Question
You receive approval for a project plan that is yet to start. You need to ensure that all project tasks start no earlier than September 13, 2010. Which project level field should you set?
Options
- AChange the Status Date field to 9/13/2010.
- BIn the Current Date field, type 9/13/2010.
- CIn the Start Date field, type 9/13/2010.
- DChange the calendar type in the Project Options dialog box.
Community Discussion
No community discussion yet for this question.