You receive approval for a project plan that is yet to start. You need to ensure that all project tasks start no earlier than September 13, 2010. Which project level field should you set?

Sign in or unlock 70-178 to reveal the answer and full explanation for question #38. The question stem and answer options stay visible for context.

Question

You receive approval for a project plan that is yet to start. You need to ensure that all project tasks start no earlier than September 13, 2010. Which project level field should you set?

Options

  • AChange the Status Date field to 9/13/2010.
  • BIn the Current Date field, type 9/13/2010.
  • CIn the Start Date field, type 9/13/2010.
  • DChange the calendar type in the Project Options dialog box.