70-178 · Question #38

70-178 Question #38: Real Exam Question with Answer & Explanation

The correct answer is C. In the Start Date field, type 9/13/2010.. See the full explanation below for the reasoning.

Question

You receive approval for a project plan that is yet to start. You need to ensure that all project tasks start no earlier than September 13, 2010. Which project level field should you set?

Options

  • AChange the Status Date field to 9/13/2010.
  • BIn the Current Date field, type 9/13/2010.
  • CIn the Start Date field, type 9/13/2010.
  • DChange the calendar type in the Project Options dialog box.