You receive approval for a project plan that is yet to start. You need to ensure that all project tasks start no earlier than September 13, 2010. Which project level field should you set?
The correct answer is C. In the Start Date field, type 9/13/2010. See the full explanation below for the reasoning.
Question
You receive approval for a project plan that is yet to start. You need to ensure that all project tasks start no earlier than September 13, 2010. Which project level field should you set?
Options
- AChange the Status Date field to 9/13/2010.
- BIn the Current Date field, type 9/13/2010.
- CIn the Start Date field, type 9/13/2010.
- DChange the calendar type in the Project Options dialog box.
How the community answered
(24 responses)- A8% (2)
- B4% (1)
- C71% (17)
- D17% (4)
Community Discussion