70-178 · Question #78
You are managing two projects in Microsoft Office Project Standard 2010. Task A in Project Alpha is dependent on Task B in Project Beta. You need to have Project automatically reschedule Task A if…
The correct answer is C. Create a master project that includes both project plans, and then create a cross-project link. See the full explanation below for the reasoning.
Question
You are managing two projects in Microsoft Office Project Standard 2010. Task A in Project Alpha is dependent on Task B in Project Beta. You need to have Project automatically reschedule Task A if Task B finishes earlier or later than scheduled. What should you do?
Options
- ADisplay the Task Drivers pane to manage the automatic rescheduling.
- BDisplay the external predecessors and successors in both project plans.
- CCreate a master project that includes both project plans, and then create a cross-project link.
- DCreate a master project that includes both project plans, and then assign the same calendar to
How the community answered
(29 responses)- A7% (2)
- B10% (3)
- C79% (23)
- D3% (1)