Microsoft
70-178 · Question #78
You are managing two projects in Microsoft Office Project Standard 2010. Task A in Project Alpha is dependent on Task B in Project Beta. You need to have Project automatically reschedule Task A if…
Sign in or unlock 70-178 to reveal the answer and full explanation for question #78. The question stem and answer options stay visible for context.
Question
You are managing two projects in Microsoft Office Project Standard 2010. Task A in Project Alpha is dependent on Task B in Project Beta. You need to have Project automatically reschedule Task A if Task B finishes earlier or later than scheduled. What should you do?
Options
- ADisplay the Task Drivers pane to manage the automatic rescheduling.
- BDisplay the external predecessors and successors in both project plans.
- CCreate a master project that includes both project plans, and then create a cross-project link.
- DCreate a master project that includes both project plans, and then assign the same calendar to
Unlock 70-178 to see the answer
You've previewed enough free 70-178 questions. Unlock 70-178 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.