70-178 · Question #78

You are managing two projects in Microsoft Office Project Standard 2010. Task A in Project Alpha is dependent on Task B in Project Beta. You need to have Project automatically reschedule Task A if…

The correct answer is C. Create a master project that includes both project plans, and then create a cross-project link. See the full explanation below for the reasoning.

Question

You are managing two projects in Microsoft Office Project Standard 2010. Task A in Project Alpha is dependent on Task B in Project Beta. You need to have Project automatically reschedule Task A if Task B finishes earlier or later than scheduled. What should you do?

Options

  • ADisplay the Task Drivers pane to manage the automatic rescheduling.
  • BDisplay the external predecessors and successors in both project plans.
  • CCreate a master project that includes both project plans, and then create a cross-project link.
  • DCreate a master project that includes both project plans, and then assign the same calendar to

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    10% (3)
  • C
    79% (23)
  • D
    3% (1)