nerdexam
Microsoft

70-178 · Question #78

70-178 Question #78: Real Exam Question with Answer & Explanation

The correct answer is C. Create a master project that includes both project plans, and then create a cross-project link.. See the full explanation below for the reasoning.

Question

You are managing two projects in Microsoft Office Project Standard 2010. Task A in Project Alpha is dependent on Task B in Project Beta. You need to have Project automatically reschedule Task A if Task B finishes earlier or later than scheduled. What should you do?

Options

  • ADisplay the Task Drivers pane to manage the automatic rescheduling.
  • BDisplay the external predecessors and successors in both project plans.
  • CCreate a master project that includes both project plans, and then create a cross-project link.
  • DCreate a master project that includes both project plans, and then assign the same calendar to

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice