70-178 · Question #79

You create a new base calendar for a project that you are tracking in Microsoft Office Project Standard 2010. You need to make this calendar the default calendar for the project. What should you do?

The correct answer is C. Set the new base calendar as the project calendar. See the full explanation below for the reasoning.

Question

You create a new base calendar for a project that you are tracking in Microsoft Office Project Standard 2010. You need to make this calendar the default calendar for the project. What should you do?

Options

  • ACreate a copy of the Standard calendar.
  • BClick the Set as Default button in the calendar options.
  • CSet the new base calendar as the project calendar.
  • DSet the new base calendar as the calendar in the Change Working Time options.

How the community answered

(37 responses)
  • A
    8% (3)
  • B
    14% (5)
  • C
    76% (28)
  • D
    3% (1)