Question

You create a new base calendar for a project that you are tracking in Microsoft Office Project Standard 2010. You need to make this calendar the default calendar for the project. What should you do?

Options

  • ACreate a copy of the Standard calendar.
  • BClick the Set as Default button in the calendar options.
  • CSet the new base calendar as the project calendar.
  • DSet the new base calendar as the calendar in the Change Working Time options.