70-178 · Question #80
In Microsoft Office Project Standard 2010, you manage a program schedule that contains multiple individual project schedules. You need to display the single critical path across all the projects…
The correct answer is D. Create a master project incorporating the individual project schedules, and select the Inserted. See the full explanation below for the reasoning.
Question
In Microsoft Office Project Standard 2010, you manage a program schedule that contains multiple individual project schedules. You need to display the single critical path across all the projects. What should you do?
Options
- Aproject to display only critical tasks
- BOpen all the project schedules, and use the Gantt Chart formatting options to display the critical
- CCreate a master project incorporating the individual project schedules, and select the Calculate
- DCreate a master project incorporating the individual project schedules, and select the Inserted
How the community answered
(40 responses)- A3% (1)
- B8% (3)
- C15% (6)
- D75% (30)