70-178 · Question #80

In Microsoft Office Project Standard 2010, you manage a program schedule that contains multiple individual project schedules. You need to display the single critical path across all the projects…

The correct answer is D. Create a master project incorporating the individual project schedules, and select the Inserted. See the full explanation below for the reasoning.

Question

In Microsoft Office Project Standard 2010, you manage a program schedule that contains multiple individual project schedules. You need to display the single critical path across all the projects. What should you do?

Options

  • Aproject to display only critical tasks
  • BOpen all the project schedules, and use the Gantt Chart formatting options to display the critical
  • CCreate a master project incorporating the individual project schedules, and select the Calculate
  • DCreate a master project incorporating the individual project schedules, and select the Inserted

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    8% (3)
  • C
    15% (6)
  • D
    75% (30)