You are starting a new project in Microsoft Office Project Standard 2010. As part of tracking this project, you will need to compare the original project schedule to the current project schedule in the default Tracking Gantt view. What should you do?
Options
- ASet a baseline.
- BSet an interim plan.
- CAdd a progress line.
- DUpdate the project tasks.