70-178 Question #82: Real Exam Question with Answer & Explanation

The correct answer is A. Create a Project Guide.. See the full explanation below for the reasoning.

Question

You are creating a project management methodology. You document project management procedures and create specialized project management process templates. You need to apply the processes in the context of Microsoft Office Project Standard 2010. What should you do first?

Options

  • ACreate a Project Guide.
  • BDisplay the Task Drivers pane.
  • CDisplay the Hyperlinks column.
  • DDisplay the Microsoft Office Online Web site.