70-178 · Question #83

A project you are tracking in Microsoft Office Project Standard 2010 is behind schedule. You are adding new tasks to the project. For each task you add, you need to see the impact on your schedule…

The correct answer is C. Turn on Show Change Highlighting. See the full explanation below for the reasoning.

Question

A project you are tracking in Microsoft Office Project Standard 2010 is behind schedule. You are adding new tasks to the project. For each task you add, you need to see the impact on your schedule. What should you do?

Options

  • ADisplay the Task Drivers pane.
  • BApply the Work Overbudget filter.
  • CTurn on Show Change Highlighting.
  • DCreate a custom filter to show all tasks with start variances.

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    14% (3)
  • C
    73% (16)
  • D
    9% (2)