Microsoft
70-178 · Question #84
70-178 Question #84: Real Exam Question with Answer & Explanation
Sign in or unlock 70-178 to reveal the answer and full explanation for question #84. The question stem and answer options stay visible for context.
Question
You are creating a project in Microsoft Office Project Standard 2010. The project has a fixed completion date. You need to have Project calculate the latest possible start date based on the fixed completion date. What should you do?
Options
- APlace a Finish No Later Than constraint on the completion milestone.
- BSet the Schedule From option in the Project Information dialog box.
- CSet the deadline date of the completion milestone to the fixed completion date.
- DSelect Tasks will always honor their constraint dates in the scheduling options.
Unlock 70-178 to see the answer
You've previewed enough free 70-178 questions. Unlock 70-178 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.