70-178 · Question #84
You are creating a project in Microsoft Office Project Standard 2010. The project has a fixed completion date. You need to have Project calculate the latest possible start date based on the fixed…
The correct answer is B. Set the Schedule From option in the Project Information dialog box. See the full explanation below for the reasoning.
Question
You are creating a project in Microsoft Office Project Standard 2010. The project has a fixed completion date. You need to have Project calculate the latest possible start date based on the fixed completion date. What should you do?
Options
- APlace a Finish No Later Than constraint on the completion milestone.
- BSet the Schedule From option in the Project Information dialog box.
- CSet the deadline date of the completion milestone to the fixed completion date.
- DSelect Tasks will always honor their constraint dates in the scheduling options.
How the community answered
(59 responses)- A12% (7)
- B81% (48)
- C5% (3)
- D2% (1)