nerdexam
Microsoft

70-178 · Question #84

70-178 Question #84: Real Exam Question with Answer & Explanation

Sign in or unlock 70-178 to reveal the answer and full explanation for question #84. The question stem and answer options stay visible for context.

Question

You are creating a project in Microsoft Office Project Standard 2010. The project has a fixed completion date. You need to have Project calculate the latest possible start date based on the fixed completion date. What should you do?

Options

  • APlace a Finish No Later Than constraint on the completion milestone.
  • BSet the Schedule From option in the Project Information dialog box.
  • CSet the deadline date of the completion milestone to the fixed completion date.
  • DSelect Tasks will always honor their constraint dates in the scheduling options.

Unlock 70-178 to see the answer

You've previewed enough free 70-178 questions. Unlock 70-178 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 70-178 Practice
You are creating a project in Microsoft Office Project Standard... | 70-178 Q#84 Answer | NerdExam