You are preparing for a presentation about a project that you are tracking in Microsoft Office Project Standard 2010. You need to create a dynamic, graphical representation of all resource work…
The correct answer is A. Create a visual report of resource work. See the full explanation below for the reasoning.
Question
You are preparing for a presentation about a project that you are tracking in Microsoft Office Project Standard 2010. You need to create a dynamic, graphical representation of all resource work, with a flexible timescale. What should you do?
Options
- ACreate a visual report of resource work.
- BCreate a custom basic report of resource work.
- CDisplay the Resource Sheet and the Work table, and then copy all the table fields into a Microsoft
- DDisplay the Resource Sheet and the Work table, and then copy a picture of them into a Microsoft
How the community answered
(31 responses)- A74% (23)
- B3% (1)
- C16% (5)
- D6% (2)
Community Discussion