You are preparing for a presentation about a project that you are tracking in Microsoft Office Project Standard 2010. You need to create a dynamic, graphical representation of all resource work…

The correct answer is A. Create a visual report of resource work. See the full explanation below for the reasoning.

Question

You are preparing for a presentation about a project that you are tracking in Microsoft Office Project Standard 2010. You need to create a dynamic, graphical representation of all resource work, with a flexible timescale. What should you do?

Options

  • ACreate a visual report of resource work.
  • BCreate a custom basic report of resource work.
  • CDisplay the Resource Sheet and the Work table, and then copy all the table fields into a Microsoft
  • DDisplay the Resource Sheet and the Work table, and then copy a picture of them into a Microsoft

How the community answered

(31 responses)
  • A
    74% (23)
  • B
    3% (1)
  • C
    16% (5)
  • D
    6% (2)