70-178 · Question #77

You are managing a project schedule in Microsoft Office Project Standard 2010. You assign one resource to a 5-day task. After completing 4 days of work, he is called away on an emergency. The…

The correct answer is C. Set the timephased work to 4 hours each for Monday and Wednesday and 0 hours for the. See the full explanation below for the reasoning.

Question

You are managing a project schedule in Microsoft Office Project Standard 2010. You assign one resource to a 5-day task. After completing 4 days of work, he is called away on an emergency. The remaining 8 hours of work are due for completion tomorrow. The resource is unable to complete the task until next week: He will work 4 hours next Monday and 4 hours next Wednesday. You need to reschedule this remaining work accurately. What should you do?

Options

  • AIn the Task Usage view, set the remaining work for the task to 8 hours.
  • BIn the Task Usage view, set the remaining duration for the task to 4 days.
  • CSet the timephased work to 4 hours each for Monday and Wednesday and 0 hours for the
  • DSet the time phased actual work to 4 hours each for Monday and Wednesday and 0 hours for the

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    12% (3)
  • C
    80% (20)
  • D
    4% (1)