Question
You are planning a project in Microsoft Office Project Standard 2010. You assign two resources 80 hours of work each for a task that has a duration of 10 days. After one week. Resource A has worked 40 hours and reports that she needs another 20 hours to complete her assignment. Resource B has worked 40 hours and reports that he needs another 60 hours to complete his assignment. Resource A and Resource B have the same skill set. You update the schedule with these hours, and the task duration changes to 12.5 days. You need to reschedule the remaining work so that the existing resources can complete the task within the original timeframe. In the Task Usage view, what should you do?
Options
- AChange Resource As remaining work to 40 hours.
- BChange Resource Bs remaining work to 40 hours.
- CChange each resource's remaining work to 40 hours.
- DChange each resources actual work to 40 hours.