In Microsoft Office Project Standard 2010, you are monitoring the progress lines and earned value of your project. You need to update the status date in the project schedule to ensure the correct…
Sign in or unlock 70-178 to reveal the answer and full explanation for question #75. The question stem and answer options stay visible for context.
Question
In Microsoft Office Project Standard 2010, you are monitoring the progress lines and earned value of your project. You need to update the status date in the project schedule to ensure the correct calculation of your projects progress. What should you do?
Options
- AEnter the appropriate status date in the Project Information dialog box.
- BEnter the appropriate status date in the project files Properties dialog box.
- CModify settings so that Project calculates progress lines based on the project status date.
- DModify settings so that Project propagates changes made to the task completion status to the