In Microsoft Office Project Standard 2010, you create a project plan for managing one-hour meetings that are part of a project. For each meeting, you create one task with a resource assignment for…
The correct answer is D. fixed units and non effort-driven. See the full explanation below for the reasoning.
Question
In Microsoft Office Project Standard 2010, you create a project plan for managing one-hour meetings that are part of a project. For each meeting, you create one task with a resource assignment for each attendee. You need to ensure that all meeting tasks show that more work is required for meetings when additional resources attend. What type of task should you set as the default?
Options
- Afixed work
- Bfixed units and effort-driven
- Cfixed duration and effort-driven
- Dfixed units and non effort-driven
How the community answered
(70 responses)- A10% (7)
- B6% (4)
- C4% (3)
- D80% (56)