Question

You are preparing a multi-year project schedule in Microsoft Office Project Standard 2010. You need to set up the schedule so you can easily switch between viewing all tasks organized by WBS and by the month they are scheduled to end. What should you do?

Options

  • ACreate a custom filter based on the Date Range filter.
  • BDefine Group By criteria for finish dates, with an interval of months.
  • CSet the project timescale to use months as the middle-tier interval.
  • DSet the project timescale to use months as the bottom-tier interval