70-178 · Question #23
You create several new tasks by using the Manually Scheduled Task option. You need to automatically calculate the start and finish dates for linked manually scheduled tasks. You need to achieve this…
The correct answer is D. Use the Respect Links feature. See the full explanation below for the reasoning.
Question
You create several new tasks by using the Manually Scheduled Task option. You need to automatically calculate the start and finish dates for linked manually scheduled tasks. You need to achieve this goal while retaining manually scheduled tasks within the project. What should you do?
Options
- AModify the values of Scheduled Start and Scheduled Finish.
- BHighlight the Project Summary task and use the Calculate Project feature.
- CInsert the task Constraint Type column and change the values for each task to the appropriate
- DUse the Respect Links feature.
How the community answered
(21 responses)- B5% (1)
- C10% (2)
- D86% (18)