nerdexam
Microsoft

70-178 · Question #22

You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?

The correct answer is B. Select the Team Planner view. See the full explanation below for the reasoning.

Question

You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?

Options

  • ASelect the Gantt Chart view, split the window, and then select the Resource Usage view for the
  • BSelect the Team Planner view.
  • CSelect the Timeline view.
  • DSelect the Gantt Chart view, and then click Assign Resources.

How the community answered

(21 responses)
  • A
    10% (2)
  • B
    71% (15)
  • C
    5% (1)
  • D
    14% (3)

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice