nerdexam
Microsoft

70-178 · Question #28

Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type. You need to ensure that the project…

The correct answer is D. Level All. See the full explanation below for the reasoning.

Question

Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type. You need to ensure that the project does not contain over-allocated resources. Which feature should you use?

Options

  • AClear Leveling
  • BAssign Resources
  • CResource Pool C Share Resources
  • DLevel All

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    19% (5)
  • C
    4% (1)
  • D
    69% (18)

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice