70-178 · Question #28
Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type. You need to ensure that the project…
The correct answer is D. Level All. See the full explanation below for the reasoning.
Question
Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type. You need to ensure that the project does not contain over-allocated resources. Which feature should you use?
Options
- AClear Leveling
- BAssign Resources
- CResource Pool C Share Resources
- DLevel All
How the community answered
(26 responses)- A8% (2)
- B19% (5)
- C4% (1)
- D69% (18)