John, a team member, will be absent from the team. A new team member, Mary, will take over Johns remaining work. You need to update the project schedule to reflect the change. You also need to…
The correct answer is A. In the Assign Resources dialog box, use the Replace feature. See the full explanation below for the reasoning.
Question
John, a team member, will be absent from the team. A new team member, Mary, will take over Johns remaining work. You need to update the project schedule to reflect the change. You also need to retain John's actual work. What should you do?
Options
- AIn the Assign Resources dialog box, use the Replace feature.
- BIn the Resource Sheet view, delete John and add Mary.
- CIn the Multiple Task Information dialog box, change the resource assignment from John to Mary.
- DIn the Resource Usage view, rename John to Mary.
How the community answered
(36 responses)- A78% (28)
- B14% (5)
- C3% (1)
- D6% (2)