70-178 · Question #30
Your project has some resources with rates that adjust over time. You need to ensure that project costs automatically adjust for these resources. What should you do?
The correct answer is A. Create cost tables to include rates that activate on effective dates. See the full explanation below for the reasoning.
Question
Your project has some resources with rates that adjust over time. You need to ensure that project costs automatically adjust for these resources. What should you do?
Options
- ACreate cost tables to include rates that activate on effective dates.
- BChange the resource availability settings to establish Units for selected dates.
- CCreate resources that include fixed Standard costs, and then apply a rate variance per project
- DCreate a named resource for each Standard hourly rate.
How the community answered
(32 responses)- A84% (27)
- B9% (3)
- C3% (1)
- D3% (1)