nerdexam
Microsoft

70-178 · Question #54

You need to set the default constraint type for all new tasks to As Late As Possible. What should you do?

The correct answer is D. In the Project Information window, from the Schedule From drop-down list box, select Project. When scheduling from the Finish Date, Project automatically assigns the As Late As Possible (ALAP) constraint to new tasks.

Planning a Project

Question

You need to set the default constraint type for all new tasks to As Late As Possible. What should you do?

Options

  • ASelect all tasks, and then click Layout.
  • BIn the Options dialog box, enable the New Tasks are effort driven check box.
  • CSelect all tasks, and then set the constraint type to As Late As Possible.
  • DIn the Project Information window, from the Schedule From drop-down list box, select Project

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    3% (1)
  • C
    14% (4)
  • D
    76% (22)

Explanation

When scheduling from the Finish Date, Project automatically assigns the As Late As Possible (ALAP) constraint to new tasks.

Topics

#constraint type#As Late As Possible#project information#scheduling defaults

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice