Question

You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?

Options

  • ASelect Task from the main ribbon menu.
  • BOn the Schedule tab of the Project options, change the New tasks created option to Manually
  • COn the Advanced tab of the Project options, clear the Automatically add new resources and tasks
  • DOn the Display tab of the Project options, clear the Edits to start and finish dates check box.
  • EClick New Tasks and change the option to Auto Scheduled.

Unlock 70-178 to see the answer

You've previewed enough free 70-178 questions. Unlock 70-178 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 70-178 Practice
You need to ensure that when you add new tasks, the project... | 70-178 Q#10 Answer | NerdExam