You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?

The correct answer is B. On the Schedule tab of the Project options, change the New tasks created option to Manually. When a task is in manually scheduled mode, the Start, Finish, and Duration columns can be

Planning a Project

Question

You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?

Options

  • ASelect Task from the main ribbon menu.
  • BOn the Schedule tab of the Project options, change the New tasks created option to Manually
  • COn the Advanced tab of the Project options, clear the Automatically add new resources and tasks
  • DOn the Display tab of the Project options, clear the Edits to start and finish dates check box.
  • EClick New Tasks and change the option to Auto Scheduled.

How the community answered

(34 responses)
  • A
    15% (5)
  • B
    74% (25)
  • C
    3% (1)
  • D
    3% (1)
  • E
    6% (2)

Explanation

When a task is in manually scheduled mode, the Start, Finish, and Duration columns can be