Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
The correct answer is B. Change the working time for the resource. See the full explanation below for the reasoning.
Question
Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
Options
- AUpdate the base project calendar.
- BChange the working time for the resource.
- CChange the maximum units for the resource.
- DAssign the resource only to tasks that are scheduled on the working days.
How the community answered
(50 responses)- A4% (2)
- B80% (40)
- C10% (5)
- D6% (3)
Community Discussion