Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?

The correct answer is B. Change the working time for the resource. See the full explanation below for the reasoning.

Question

Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?

Options

  • AUpdate the base project calendar.
  • BChange the working time for the resource.
  • CChange the maximum units for the resource.
  • DAssign the resource only to tasks that are scheduled on the working days.

How the community answered

(50 responses)
  • A
    4% (2)
  • B
    80% (40)
  • C
    10% (5)
  • D
    6% (3)