Question

Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?

Options

  • AUpdate the base project calendar.
  • BChange the working time for the resource.
  • CChange the maximum units for the resource.
  • DAssign the resource only to tasks that are scheduled on the working days.

Unlock 70-178 to see the answer