Microsoft
70-178 · Question #55
You manage a project according to the schedule as shown in the exhibit. (Click the Exhibit button.) You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
The correct answer is D. Set Task 4 as manually scheduled. The Gantt bar for task 6 indicates that it is a manually scheduled task.
Planning a Project
Question
You manage a project according to the schedule as shown in the exhibit. (Click the Exhibit button.) You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
Exhibit
Options
- ACreate a task dependency from Task 4 to Task 6.
- BSet Task 4 as critical.
- CAdd a 1 day lead to Task 4.
- DSet Task 4 as manually scheduled.
How the community answered
(30 responses)- A3% (1)
- B17% (5)
- C7% (2)
- D73% (22)
Explanation
The Gantt bar for task 6 indicates that it is a manually scheduled task.
Topics
#task mode#manual scheduling#auto scheduled#task settings
Community Discussion
No community discussion yet for this question.
