nerdexam
Microsoft

70-178 · Question #55

You manage a project according to the schedule as shown in the exhibit. (Click the Exhibit button.) You need to set the Task Mode for task 4 to be the same as task 6. What should you do?

The correct answer is D. Set Task 4 as manually scheduled. The Gantt bar for task 6 indicates that it is a manually scheduled task.

Planning a Project

Question

You manage a project according to the schedule as shown in the exhibit. (Click the Exhibit button.) You need to set the Task Mode for task 4 to be the same as task 6. What should you do?

Exhibit

70-178 question #55 exhibit

Options

  • ACreate a task dependency from Task 4 to Task 6.
  • BSet Task 4 as critical.
  • CAdd a 1 day lead to Task 4.
  • DSet Task 4 as manually scheduled.

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    17% (5)
  • C
    7% (2)
  • D
    73% (22)

Explanation

The Gantt bar for task 6 indicates that it is a manually scheduled task.

Topics

#task mode#manual scheduling#auto scheduled#task settings

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice