Microsoft
70-178 · Question #70
70-178 Question #70: Real Exam Question with Answer & Explanation
The correct answer is C. Enter task IDs in the Predecessors column.. See the full explanation below for the reasoning.
Question
You are using Microsoft Office Project Standard 2010 to create a project schedule in which you will be tracking the critical path of a set of linked tasks. When you add new tasks, their start dates default to the project start date. You need to order the tasks on a timeline so that you can analyze the critical path. What should you do?
Options
- AEnter starting dates for the tasks.
- BAssign resources, and then level them.
- CEnter task IDs in the Predecessors column.
- DDrag the tasks to their correct starting dates.
Community Discussion
No community discussion yet for this question.