You are building a project plan in Microsoft Office Project Standard 2010. You expand the project plan to display all outline levels and the project summary task. You enter resources and their…
The correct answer is A. Display the cost of Task 0. See the full explanation below for the reasoning.
Question
You are building a project plan in Microsoft Office Project Standard 2010. You expand the project plan to display all outline levels and the project summary task. You enter resources and their costs. You have not yet set a baseline. You need to estimate the total cost of the project. What should you do?
Options
- ADisplay the cost of Task 0.
- BDisplay the estimate at completion (EAC) field.
- CDisplay the Budget Cost column in the Task and Resource Usage views.
- DAssign the resources to the project summary task, and then display the task resources.
How the community answered
(35 responses)- A71% (25)
- B17% (6)
- C9% (3)
- D3% (1)