Microsoft
70-178 · Question #71
70-178 Question #71: Real Exam Question with Answer & Explanation
Sign in or unlock 70-178 to reveal the answer and full explanation for question #71. The question stem and answer options stay visible for context.
Question
You are building a project plan in Microsoft Office Project Standard 2010. You expand the project plan to display all outline levels and the project summary task. You enter resources and their costs. You have not yet set a baseline. You need to estimate the total cost of the project. What should you do?
Options
- ADisplay the cost of Task 0.
- BDisplay the estimate at completion (EAC) field.
- CDisplay the Budget Cost column in the Task and Resource Usage views.
- DAssign the resources to the project summary task, and then display the task resources.
Unlock 70-178 to see the answer
You've previewed enough free 70-178 questions. Unlock 70-178 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.