Question
In Microsoft Office Project 2010, you create a new task in a project plan, and assign a resource to the task. The default task duration is 1 day, and the default amount of work is 7 hours. You need to change the calendar options to set the default amount of work to 8 hours. What should you do?
Options
- ASet the hours per day to 8.
- BSet the hours per week to 40.
- CSet the days per month to 20.
- DSet the default start time to 8:00 A.M. and the default end time to 4:00 P.M.