Question

In Microsoft Office Project 2010, you create a new task in a project plan, and assign a resource to the task. The default task duration is 1 day, and the default amount of work is 7 hours. You need to change the calendar options to set the default amount of work to 8 hours. What should you do?

Options

  • ASet the hours per day to 8.
  • BSet the hours per week to 40.
  • CSet the days per month to 20.
  • DSet the default start time to 8:00 A.M. and the default end time to 4:00 P.M.

Unlock 70-178 to see the answer