You need to ensure that you can view only the tasks on your projects critical path. What should you do?
The correct answer is C. View the project's Gantt chart and apply the Critical filter. See the full explanation below for the reasoning.
Question
You need to ensure that you can view only the tasks on your projects critical path. What should you do?
Options
- AOn the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths
- BView the projects Gantt chart and apply the Critical group.
- CView the project's Gantt chart and apply the Critical filter.
- DOn the Advanced tab of the Project 2010 options, modify the Tasks are critical if slack is less than
How the community answered
(62 responses)- A5% (3)
- B3% (2)
- C79% (49)
- D13% (8)