You update your project schedule based on information received from your team members in today's status meeting. You need to compare the current revised project schedule with the baseline schedule…
The correct answer is D. Tracking Gantt. See the full explanation below for the reasoning.
Question
You update your project schedule based on information received from your team members in today's status meeting. You need to compare the current revised project schedule with the baseline schedule side by side. Which default view should you use?
Options
- ACalendar
- BMultiple Baselines Gantt
- CLeveling Gantt
- DTracking Gantt
- ETimeline
How the community answered
(30 responses)- A3% (1)
- B7% (2)
- C3% (1)
- D70% (21)
- E17% (5)