Question
Your project contains many tasks that have dependencies and result in independent networks of tasks. You need to ensure that you can view critical tasks on all independent networks of tasks within the project. What should you do?
Options
- AView the project's Gantt chart and apply the Critical filter.
- BOn the Advanced tab of the Microsoft Project 2010 options, select the Calculate multiple critical
- CView the project's Gantt chart and apply the Critical group.
- DOn the Advanced tab of the Microsoft Project 2010 options, modify the Tasks are critical if slack is