nerdexam
Microsoft

70-178 · Question #64

Your project contains many tasks that have dependencies and result in independent networks of tasks. You need to ensure that you can view critical tasks on all independent networks of tasks within…

The correct answer is B. On the Advanced tab of the Microsoft Project 2010 options, select the Calculate multiple critical. You can calculate and display a critical path for each independent network of tasks within the Click the File tab, and then click Options. In the Project Options dialog box, click Advanced, and then select the Calculate multiple critical paths check box. By default, Project…

Monitoring and Controlling a Project

Question

Your project contains many tasks that have dependencies and result in independent networks of tasks. You need to ensure that you can view critical tasks on all independent networks of tasks within the project. What should you do?

Options

  • AView the project's Gantt chart and apply the Critical filter.
  • BOn the Advanced tab of the Microsoft Project 2010 options, select the Calculate multiple critical
  • CView the project's Gantt chart and apply the Critical group.
  • DOn the Advanced tab of the Microsoft Project 2010 options, modify the Tasks are critical if slack is

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    81% (25)
  • C
    10% (3)
  • D
    3% (1)

Explanation

You can calculate and display a critical path for each independent network of tasks within the Click the File tab, and then click Options. In the Project Options dialog box, click Advanced, and then select the Calculate multiple critical paths check box. By default, Project sets the late finish date for tasks without successors or constraints to be the project finish date. If you choose to calculate multiple critical paths, Project sets the late finish date for these tasks to be their early finish date, making the task critical.

Topics

#critical path#multiple critical paths#independent networks#slack calculation

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice