nerdexam
Microsoft

70-178 · Question #51

You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display…

The correct answer is A. Set the Deadline date field. Deadline dates don't usually affect task scheduling. They are used to indicate a target date you don't want to miss, without requiring you to set a task constraint that could affect scheduling if predecessor tasks change. A task with a deadline is scheduled just like any other…

Monitoring and Controlling a Project

Question

You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted finish date on the default Gantt chart. What should you modify in the Task Information window?

Options

  • ASet the Deadline date field.
  • BSet the Constraint date field.
  • CSet the Finish date field.
  • DSelect the Mark task as milestone check box.
  • ESelect the Display on Timeline check box.

How the community answered

(23 responses)
  • A
    83% (19)
  • B
    9% (2)
  • C
    4% (1)
  • E
    4% (1)

Explanation

Deadline dates don't usually affect task scheduling. They are used to indicate a target date you don't want to miss, without requiring you to set a task constraint that could affect scheduling if predecessor tasks change. A task with a deadline is scheduled just like any other task.

Topics

#deadline date#Gantt chart#task information#targeted finish

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice