nerdexam
Microsoft

70-178 · Question #52

70-178 Question #52: Real Exam Question with Answer & Explanation

Sign in or unlock 70-178 to reveal the answer and full explanation for question #52. The question stem and answer options stay visible for context.

Question

The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?

Options

  • ASelect the Project Summary Task option.
  • BSelect the Summary Tasks option.
  • CCreate a manually scheduled summary task.
  • DUpdate the project calendar.

Unlock 70-178 to see the answer

You've previewed enough free 70-178 questions. Unlock 70-178 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 70-178 Practice
The first major phase of your project is scheduled for a duration... | 70-178 Q#52 Answer | NerdExam