70-178 · Question #52
The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project…
The correct answer is C. Create a manually scheduled summary task. See the full explanation below for the reasoning.
Question
The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?
Options
- ASelect the Project Summary Task option.
- BSelect the Summary Tasks option.
- CCreate a manually scheduled summary task.
- DUpdate the project calendar.
How the community answered
(39 responses)- A8% (3)
- B5% (2)
- C74% (29)
- D13% (5)