nerdexam
Microsoft

70-178 · Question #50

70-178 Question #50: Real Exam Question with Answer & Explanation

The correct answer is C. Open a blank project and select Insert Subproject for each project schedule.. See the full explanation below for the reasoning.

Question

You manage several projects. Each project has shared resources and work distribution. You need to ensure that you can adjust the workload for specific resources used across multiple project schedules. What should you do?

Options

  • AEnable the Load Summary Resource Assignments option.
  • BOpen the individual schedules and use the Visual Reports option.
  • COpen a blank project and select Insert Subproject for each project schedule.
  • DOpen the shared Resource Pool for each project schedule.

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice