Question
You manage several projects. Each project has shared resources and work distribution. You need to ensure that you can adjust the workload for specific resources used across multiple project schedules. What should you do?
Options
- AEnable the Load Summary Resource Assignments option.
- BOpen the individual schedules and use the Visual Reports option.
- COpen a blank project and select Insert Subproject for each project schedule.
- DOpen the shared Resource Pool for each project schedule.