70-178 · Question #49

You have a Project 2010 schedule that contains the following tasks: - Inactive tasks - Manually scheduled tasks - Manually scheduled summary tasks - Tasks that contain strikethrough font You want to…

The correct answer is C. Change all manually scheduled summary tasks to automatic scheduling. When a Project 2010 project is saved as a Project 2007 project, summary tasks that are manually scheduled in Project 2010 are set to milestone tasks in Project 2007.

Executing a Project

Question

You have a Project 2010 schedule that contains the following tasks:

  • Inactive tasks
  • Manually scheduled tasks
  • Manually scheduled summary tasks
  • Tasks that contain strikethrough font

You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are created. What should you do?

Options

  • AChange all inactive tasks to active tasks.
  • BChange all tasks that contain strikethrough font to tasks that include normal font.
  • CChange all manually scheduled summary tasks to automatic scheduling.
  • DChange all manually scheduled tasks to automatic scheduling.

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    3% (1)
  • C
    76% (22)
  • D
    14% (4)

Explanation

When a Project 2010 project is saved as a Project 2007 project, summary tasks that are manually scheduled in Project 2010 are set to milestone tasks in Project 2007.