Microsoft
70-178 · Question #49
You have a Project 2010 schedule that contains the following tasks: - Inactive tasks - Manually scheduled tasks - Manually scheduled summary tasks - Tasks that contain strikethrough font You want to…
The correct answer is C. Change all manually scheduled summary tasks to automatic scheduling. When a Project 2010 project is saved as a Project 2007 project, summary tasks that are manually scheduled in Project 2010 are set to milestone tasks in Project 2007.
Executing a Project
Question
You have a Project 2010 schedule that contains the following tasks:
- Inactive tasks
- Manually scheduled tasks
- Manually scheduled summary tasks
- Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are created. What should you do?
Options
- AChange all inactive tasks to active tasks.
- BChange all tasks that contain strikethrough font to tasks that include normal font.
- CChange all manually scheduled summary tasks to automatic scheduling.
- DChange all manually scheduled tasks to automatic scheduling.
How the community answered
(29 responses)- A7% (2)
- B3% (1)
- C76% (22)
- D14% (4)
Explanation
When a Project 2010 project is saved as a Project 2007 project, summary tasks that are manually scheduled in Project 2010 are set to milestone tasks in Project 2007.
Topics
#file compatibility#manually scheduled summary tasks#Project 2007#backward compatibility
Community Discussion