A section of your project contains only a summary task along with four subtasks and a milestone. You discover that the section is located in the incorrect phase and has the incorrect Work Breakdown…

The correct answer is C. Drag the summary task. See the full explanation below for the reasoning.

Question

A section of your project contains only a summary task along with four subtasks and a milestone. You discover that the section is located in the incorrect phase and has the incorrect Work Breakdown Structure (WBS) numbering. You need to move the section to another phase of the project. You also need to ensure that the section reflects the correct WBS numbering. What should you do?

Options

  • ASelect the summary task and change the scheduling mode to Manually Scheduled.
  • BSelect the entire section and click Move Task.
  • CDrag the summary task.
  • DModify the start and finish dates of the summary task.

How the community answered

(45 responses)
  • A
    11% (5)
  • B
    7% (3)
  • C
    80% (36)
  • D
    2% (1)