The correct answer is B. On the Schedule tab of the Project 2010 options, clear the Autolink inserted or moved tasks. See the full explanation below for the reasoning.
Question
Every time you create a new task within your project schedule, Project 2010 automatically adds a dependency to the new task. You need to turn off the feature that triggers the dependency to be automatically added. What should you do?
Options
- AOn the Advanced tab of the Project 2010 options, clear the Move selection after enter check box.
- BOn the Schedule tab of the Project 2010 options, clear the Autolink inserted or moved tasks
- COn the Advanced tab of the Project 2010 options, select the Ask to update automatic links check
- DHighlight all tasks and select Respect Links.