You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to…

The correct answer is D. Create a base calendar for each shift. See the full explanation below for the reasoning.

Question

You have team members who work on one of the following shifts:

Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts. What should you do?

Options

  • ACreate shift resource departments.
  • BChange the maximum units for each resource.
  • CCreate three tasks, one for each shift.
  • DCreate a base calendar for each shift.

How the community answered