Microsoft
70-178 · Question #65
You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to…
The correct answer is D. Create a base calendar for each shift. See the full explanation below for the reasoning.
Question
You have team members who work on one of the following shifts:
Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts. What should you do?
Options
- ACreate shift resource departments.
- BChange the maximum units for each resource.
- CCreate three tasks, one for each shift.
- DCreate a base calendar for each shift.
How the community answered
(36 responses)- A8% (3)
- B6% (2)
- C3% (1)
- D83% (30)
Community Discussion
No community discussion yet for this question.