Your project contains several baselines. By mistake, you save one of your baselines in Baseline5. You need to move Baseline5 to Baseline3 while preserving the baseline information. You also need to…
The correct answer is C. From the Set Baseline window, click Set interim plan and copy Baseline5 into Baseline3. E. From the Set Baseline window, click Set Baseline and select Baseline5. See the full explanation below for the reasoning.
Question
Your project contains several baselines. By mistake, you save one of your baselines in Baseline5. You need to move Baseline5 to Baseline3 while preserving the baseline information. You also need to create a new Baseline5 by using today's data. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Options
- AFrom the Clear Baseline window, click Clear baseline plan and select Baseline3.
- BFrom the Clear Baseline window, click Clear baseline plan and select Baseline5.
- CFrom the Set Baseline window, click Set interim plan and copy Baseline5 into Baseline3.
- DFrom the Set Baseline window, click Set Baseline and select Baseline3.
- EFrom the Set Baseline window, click Set Baseline and select Baseline5.
How the community answered
(42 responses)- A2% (1)
- B7% (3)
- C74% (31)
- D17% (7)