You enter the finish date for a task, and then assign a resource. You discover that the task is automatically scheduled for two weeks past the finish date you have entered. You need to identify the…

The correct answer is C. Use the Task Inspector tool and view the resource calendar. See the full explanation below for the reasoning.

Question

You enter the finish date for a task, and then assign a resource. You discover that the task is automatically scheduled for two weeks past the finish date you have entered. You need to identify the problem. What should you do?

Options

  • AClick Calculate project
  • BUse the Task Inspector tool and view the start and finish dates
  • CUse the Task Inspector tool and view the resource calendar
  • DView the deadline date for the task

How the community answered

(53 responses)
  • A
    8% (4)
  • B
    4% (2)
  • C
    74% (39)
  • D
    15% (8)