Question
One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?
Options
- AThe task is early by 14 days.
- BThe task is early by 4 days.
- CThe task is late by 4 days.
- DThe task is late by 14 days.