Question

One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?

Options

  • AThe task is early by 14 days.
  • BThe task is early by 4 days.
  • CThe task is late by 4 days.
  • DThe task is late by 14 days.