Microsoft
70-178 · Question #60
One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?
The correct answer is C. The task is late by 4 days. See the full explanation below for the reasoning.
Question
One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?
Options
- AThe task is early by 14 days.
- BThe task is early by 4 days.
- CThe task is late by 4 days.
- DThe task is late by 14 days.
How the community answered
(51 responses)- A14% (7)
- B4% (2)
- C76% (39)
- D6% (3)
Community Discussion
No community discussion yet for this question.