70-178 · Question #60

One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?

The correct answer is C. The task is late by 4 days. See the full explanation below for the reasoning.

Question

One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?

Options

  • AThe task is early by 14 days.
  • BThe task is early by 4 days.
  • CThe task is late by 4 days.
  • DThe task is late by 14 days.

How the community answered

(51 responses)
  • A
    14% (7)
  • B
    4% (2)
  • C
    76% (39)
  • D
    6% (3)