nerdexam
Microsoft

70-178 · Question #2

You use Project Professional 2010 to manage a software development project as shown in the exhibit. (Click the Exhibit button.) You need to cancel the Develop prototype based on functional…

The correct answer is C. Inactivate the task. E. Create a link from the Develop functional specifications task to the Review functional specifications task. See the full explanation below for the reasoning.

Question

You use Project Professional 2010 to manage a software development project as shown in the exhibit. (Click the Exhibit button.) You need to cancel the Develop prototype based on functional specifications task. You also need to retain all the information from the task. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

Exhibit

70-178 question #2 exhibit

Options

  • ADelete the task.
  • BSet the tasks remaining work to 0 hours.
  • CInactivate the task.
  • DMake the task 100 percent complete.
  • ECreate a link from the Develop functional specifications task to the Review functional specifications task.

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    83% (30)
  • D
    8% (3)

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice