Question
You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
Options
- AHighlight the two tasks.
- BHighlight the summary task. Click Set Baseline and select Baseline1.
- CHighlight the summary task.
- DHighlight the two tasks.