You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
The correct answer is A. Highlight the two tasks. See the full explanation below for the reasoning.
Question
You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
Options
- AHighlight the two tasks.
- BHighlight the summary task. Click Set Baseline and select Baseline1.
- CHighlight the summary task.
- DHighlight the two tasks.
How the community answered
(17 responses)- A71% (12)
- B18% (3)
- C6% (1)
- D6% (1)