You need to view Task ID 0 on your project plan. What should you do?
The correct answer is C. On the Format tab, select Project Summary Task. See the full explanation below for the reasoning.
Question
You need to view Task ID 0 on your project plan. What should you do?
Options
- AOn the Advanced tab of the Project 2010 options, select Show Status Bar.
- BOn the Format tab, select Summary Tasks.
- COn the Format tab, select Project Summary Task.
- DInsert a new Summary Task.
How the community answered
(41 responses)- A17% (7)
- B7% (3)
- C73% (30)
- D2% (1)