PSM-II · Question #121
PSM-II Question #121: Real Exam Question with Answer & Explanation
The correct answer is B. The Development Team informs Paul that the progress he has perceived to date is not correct.. Scrum is founded on empirical process control and asserts that knowledge comes from experience and making decisions based on what is known. Scrum employs an iterative, incremental approach to optimize predictability and control risk. At the end of every Sprint, an increment of `d
Question
Options
- AIn the next Sprints, the Development Team strives to make the selected work as close to `done'
- BThe Development Team informs Paul that the progress he has perceived to date is not correct.
- CThe Scrum Master will manage the Sprint Backlog and assign work to the Development Team
- DThe Scrum Master sets the open work aside to be performed in one or more release Sprints.
Explanation
Scrum is founded on empirical process control and asserts that knowledge comes from experience and making decisions based on what is known. Scrum employs an iterative, incremental approach to optimize predictability and control risk. At the end of every Sprint, an increment of `done' work must be available in order to inspect and adapt accordingly.