nerdexam
Scrum

PSM-II · Question #121

PSM-II Question #121: Real Exam Question with Answer & Explanation

The correct answer is B. The Development Team informs Paul that the progress he has perceived to date is not correct.. Scrum is founded on empirical process control and asserts that knowledge comes from experience and making decisions based on what is known. Scrum employs an iterative, incremental approach to optimize predictability and control risk. At the end of every Sprint, an increment of `d

Question

Paul is a Product Owner for multiple products. Each product is allocated a dedicated Scrum Team and a set budget. Based on the average velocity of a previous product release, Paul had estimated a new product to take 9 Sprints to complete. The average velocity of the previous product release was 50 completed units of work per Sprint. Over the first 3 Sprints, the Development Team reported an average velocity of 40 completed units per Sprint, while not fully completing the required integration tests. The Development Team estimates that integration testing would require additional effort to make the increments shippable. The Development Team is unsure if the required velocity is achievable. What is the most effective way to recover?

Options

  • AIn the next Sprints, the Development Team strives to make the selected work as close to `done'
  • BThe Development Team informs Paul that the progress he has perceived to date is not correct.
  • CThe Scrum Master will manage the Sprint Backlog and assign work to the Development Team
  • DThe Scrum Master sets the open work aside to be performed in one or more release Sprints.

Explanation

Scrum is founded on empirical process control and asserts that knowledge comes from experience and making decisions based on what is known. Scrum employs an iterative, incremental approach to optimize predictability and control risk. At the end of every Sprint, an increment of `done' work must be available in order to inspect and adapt accordingly.

Community Discussion

No community discussion yet for this question.

Full PSM-II Practice