PSM-II · Question #134
A Scrum Team has requested a hardening Sprint to integrate the work produced in previous Sprints and test before releasing. What three scenarios has likely occurred? (Choose three.)
The correct answer is A. The team's Definition of Done is not being adhered to during every Sprint. B. The team's Definition of Done is weak or incomplete causing a build up of technical debt. C. The Development Team is having difficulties with the ability to regularly release during a Sprint. At the end of a Sprint, the new Increment must be `Done', which means it must be in useable condition and meet the Scrum Team's Definition of Done.
Question
A Scrum Team has requested a hardening Sprint to integrate the work produced in previous Sprints and test before releasing. What three scenarios has likely occurred? (Choose three.)
Options
- AThe team's Definition of Done is not being adhered to during every Sprint.
- BThe team's Definition of Done is weak or incomplete causing a build up of technical debt.
- CThe Development Team is having difficulties with the ability to regularly release during a Sprint.
- DHardening Sprints are supported by the Scrum framework so this is acceptable.
- EScrum has been customized in a suitable manner to make the previous work releasable.
How the community answered
(19 responses)- A84% (16)
- D5% (1)
- E11% (2)
Explanation
At the end of a Sprint, the new Increment must be `Done', which means it must be in useable condition and meet the Scrum Team's Definition of Done.