PSM-II · Question #6

Steven, who is a Scrum Master, on one of the Scrum Teams has approached you asking for advice. Their Daily Scrum requires more than 15 minutes and the team has suggested dividing themselves into two…

The correct answer is C. Unsure ?dividing a team into two cannot be decided based on this information. You offer to. The relationship between cause and effect can become more clear when more information

Solving Problems

Question

Steven, who is a Scrum Master, on one of the Scrum Teams has approached you asking for advice. Their Daily Scrum requires more than 15 minutes and the team has suggested dividing themselves into two separate teams in order to stay within the time box. As another Scrum Master, what would be the best response?

Options

  • AAgree ?this is an appropriate solution to the problem.
  • BDisagree ?as the root cause may not be that the team is too big.
  • CUnsure ?dividing a team into two cannot be decided based on this information. You offer to
  • DAgree ?You agree that dividing the team into two is a good strategy to allow the teams to learn

How the community answered

(60 responses)
  • A
    12% (7)
  • B
    17% (10)
  • C
    68% (41)
  • D
    3% (2)

Explanation

The relationship between cause and effect can become more clear when more information

Topics

#Daily Scrum#team size#root cause analysis#Scrum Master role