nerdexam
Scrum

PSM-II · Question #20

A Development Team member has notified the Scrum Master of a potential data security risk. What action should the Scrum Master take?

The correct answer is C. Ask the Development Team member to share the issue with the team as soon as possible. It is best to coach the Development Team members to collaborate on issues regardless of severity. They may consult the Scrum Master of Product Owner if needed.

Solving Problems

Question

A Development Team member has notified the Scrum Master of a potential data security risk. What action should the Scrum Master take?

Options

  • ANotify the test team.
  • BAdd a Product Backlog item to address the security issue.
  • CAsk the Development Team member to share the issue with the team as soon as possible.
  • DWait until the Sprint Retrospective to add security to the definition of "Done".

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    5% (2)
  • C
    78% (32)
  • D
    12% (5)

Explanation

It is best to coach the Development Team members to collaborate on issues regardless of severity. They may consult the Scrum Master of Product Owner if needed.

Topics

#security risk#transparency#Development Team#Scrum Master role

Community Discussion

No community discussion yet for this question.

Full PSM-II Practice