Question
A Development Team, that has remote team members, typically spends time before the Daily Scrum to setup the meeting rooms and conference calling equipment and tools in order to have their Daily Scrum. How should the Scrum Master handle this situation?
Options
- AAllow the Development Team to self-manage and decide for itself what to do.
- BSetup the meeting and tell the Development Team that is how it will be done.
- CAsk the Development Team members to alternate who is responsible for meeting setup.
- DInform management and ask them to solve it.