PSM-II Question #131: Real Exam Question with Answer & Explanation
The correct answer is B. Discuss the situation with the Scrum Team. Help them find improved ways to clarify and set a. See the full explanation below for the reasoning.
Question
Relationships between the Product Owner and Development team have been tense for many Sprints. The Product Owner has lost trust and respect for the Development Team as they consistently fail to achieve the Sprint Goal to her satisfaction by the end of each Sprint. The Development Team blame the Product Owner for increasing scope each Sprint making the Sprint Goal unachievable. As a Scrum Master, what should you do?
Options
- ASpeak to the line managers of the various Development Team members about their lack of
- BDiscuss the situation with the Scrum Team. Help them find improved ways to clarify and set a
- CTake no action. Allow the Development Team to self organise to address the issue
- DTalk to the Product Owner and tell them not to increase scope mid Sprint