PSM-II · Question #157
Over the course of several Sprints, the relationship between the Product Owner and the Development team has suffered. The Development Team is upset with the Product Owner for the constantly changing…
The correct answer is A. During the Sprint Retrospective, ask the Product Owner and the Development Team to address. Conflicts are a natural occurrence and the Scrum Master coaches the Development Team on the value of resolving conflicts. Leaving conflicts unresolved can impact the Scrum values of openness and respect diminishing trust. Lower trust levels will impact the Scrum Team's…
Question
Over the course of several Sprints, the relationship between the Product Owner and the Development team has suffered. The Development Team is upset with the Product Owner for the constantly changing the upcoming items for the product. The Product Owner is upset with the Development Team for changing the work that needs to be done during the Sprint. What should Steven, the Scrum Master, do?
Options
- ADuring the Sprint Retrospective, ask the Product Owner and the Development Team to address
- BThe Scrum Master's responsibility is to ensure the Development Team has a stable velocity. Any
- CTake the time between Sprints to organize a team building session to rebuild the relationship.
- DExplain to the Development Team that the Product Owner is accountable for flow of value and
How the community answered
(24 responses)- A54% (13)
- B8% (2)
- C25% (6)
- D13% (3)
Explanation
Conflicts are a natural occurrence and the Scrum Master coaches the Development Team on the value of resolving conflicts. Leaving conflicts unresolved can impact the Scrum values of openness and respect diminishing trust. Lower trust levels will impact the Scrum Team's effectiveness and can cause impediments in the future. It is the responsibility of the Scrum Master to remove impediments that hinder the team through conflict resolution and facilitation.